CGS § 42-158k. Retainage limitation. Payment by owner. Time limits.
No construction contract may provide for any retainage in an amount that exceeds five per cent of the estimated amount of a progress payment for the life of the construction project. All retainage shall be paid by the owner not later than thirty days after the issuance of a certificate of final completion by the owner or the owner's authorized representative or not later than thirty days after the equivalent written acceptance of the construction project work by the owner.
PreviousCGS § 42-158j. Required contract provisions re timely payment of contractors, subcontractors and suppliers. Payment requisition statement. Remedy for untimely payments. Penalties. Escrow accounts. Withholding payments due because of disputes prohibited. Progress payments. Rights of action.NextCGS § 42-158l. Clauses waiving right to claim mechanic's lien or claim against a payment bond void.